Monday August 18, 2014

Other than wind turbines and the 49 outstanding BBOXXs, the system is up and running. Symons house and the kiosk have been running off pv panels and batteries for three days. All appears well. The BBOXXs that we do have will be tested today. It is not clear when they are fully charged so we charged them overnight to be sure. It is likely that some are bad and will need to be returned. I will work out with Anshul the delivery date and getting accessories. Stay tuned.


The data logger is working, after two full days of troubleshooting. We have confirmed that the data are available on the server in Seattle. We are using data on the sim card at a high rate. Daniel will troubleshoot that.